PROJECT LOKA UPDATE - 151119
MVP Phase 1 (MEP / Beta Version for Internal) - we are aiming to finish the majority of MEP Eng development by early Dec
- Currently engineers are working on the FE BE integration process in staging & also bug fixing from QA testing , we expect more integration will happen in the next upcoming weeks.
- Once things are working fine, we will continue on bugfixing. Be aware that the current plan the BE will only be available on staging and we will not release the MEP App to Apple/Playstore yet.
- FE Web is still working on the Internal Tools and Web Flow (Landing & POI Page).
MVP Phase 2 (MVP - Open for Public) - will start the proper Eng sizing and timeline plotting for MVP by early Dec. No exact date yet on the MVP Launch but current target is within Q1 2020
- Majority of the product requirement for MVP has been finalized, some are still under interation. The MVP version will also include Product Features (User Profile, Content Creation, Occasion-based Discovery, Gamification, etc) and also Data Tracking & Marketing Technology Solution.
- Apart from working on MEP version, currently some FE App have started the development of MVP Components. BE has not started yet.
- We have been working closely with Marketing to define the GTM and any Mktg strategies. Also once the MVP requirement has clearly finalized, we will conduct follow up meeting with Cust Ops, Legal, Finance, etc to confirm their support & adjustment on Ops Handling, TnC, Privacy Policy, etc.
Post MVP Roadmap - we estimated more Post MVP Requirement will be delivered by Design team staggeredly starting end of Nov till mid of Feb.
- Currently the design team are focusing on finishing some MVP Req and some have started working on the Post MVP Requirement e.g. Referral, Sharing, Digitalized Menu, etc.
- The current target is to let Eng start working on those Post MVP Features by end of Q1 2020 & hopefully we can release some of those in Q2 2020.
- Apart from MEP and MVP Project Management, product team is also detailing out the Q3 and Q4 2020 commitment right now.
Feel free to check the project timeline for more detailed update or slack @robert if you have any queries / concerns. https://docs.google.com/spreadsheets/d/1NF0y4v_l3Qqkjusq-sXPtV74BmnOS24SZnlIHTvg5q4/edit#gid=500722425\