PMO division:
--> @Yussi will setup PMO division to oversees project across stream (in order to identify the dependency of projects in between stream).
--> Hiring still in progress.
Tripops decommission:
--> Testing done by @kenny.
ECI:
--> ERP Assigned Payment ready in Data Lake.
Payment:
--> Coupon Santa Fraud - quick fix done, will be fixed the root cause by Rewards Product Team.
-> Found bug in the code, @hartanto.hartanto will do the load test to know the processing time this week.
-> POC done, design review still in progress by @hadi.japarto.
-> Fintools will be rebranded become BP UI.
--> There's additional requirements for fintools from loyalty points @anastasia @winnie.
--> @khresna & @Ridwan will discuss with @Nazmy related to Front End Engineer.
-> Update from Flight, Accom and Payment Product, there's no plan for AWS Multiaccount in Q3.
-> QA Manager is in interview process.
-> 3 persons still in VPS Project until June, will do transition to Product Integration in Q3.
-> PM & Eng Lead to fullfill @agusputri document.
https://docs.google.com/spreadsheets/d/1bmZA3adXueCdHDiHYo5RPHqIf94J2mILbjObStanD6A/edit#gid=886735410
Next Action Point:
=> Khresna: will simplify some reports to reduce number of reports under data team pipeline, deposit waiting for Accom.
=> Many reports from FBI are still there.
=> FBI need eng to move the reports.
=> Merlin will have a meeting with Elsa, together with Khresna, Chriswanto & Aji to discuss reports specific to Accom.
=> Ale: all reports from financial product are already registered on the spreadsheet.