[MoM Weekly PM - Eng Lead - Architect] 10 June 2019

ECI Integration --> IN PROGRESS

Blocker for the Integration:
EMR setup, not available in the ECI document -> DONE
Crossed date issue -> DONE. data size is still manageable
Next Action Point:
@hartanto.hartanto will do the load test to know the processing time --> Data just confirmed available by today.

Tera Deposit -->IN PROGRESS (TERA timeline integration starting Q3)

Deposit project sprint is agreed to be separated with Phoenix, Accom will do the development in BP v3 first. If the timeline met, will move it to BP next gen.
Next Action Point:
@hadi.japarto: finished the design review by this week. Designed by ICAN - TERA ask for 2 phase commit with timeout

TBI data to Data Lake IN PROGRESS - V3

Already discussed with site infra, approved. @Nazmy will follow up by ticket.

Next action point:
with bot-play @hartanto will do the follow up DONE
https://29022131.atlassian.net/wiki/spaces/ECI/pages/1026392810/BP+TBI+-+Test+Data+-+Sync

Fintools Future Roadmap - IN PROGRESS

Apparently oracle is treated treated as sensitive application by site infra, other application should not be able to establish direct connection with oracle
@khresna has shared the requirements to Marc, Nazmy, and Hadi
Yussi and Nazmy already discuss Fintools with Ben and Marc. In short, we will use Oracle if feature exist in Oracle, and in the mean time we will go with Fintool since our maintenance cost is low and there are no urgency yet to move out from Fintool but the assesment for new feature need to consider the Oracle too.

Next Action Point:

AWS Multiaccount IN PROGRESS

for task handler perlu private link klo multiaccount.
Kenny already share list ERP report & dependencies
As dicussed, we will leave big DB will be as it is, and smaller on expected to use API from product if possible

Next Action Point:
PMs and Eng lead need to add this in quarterly planning discussion with products. especially Flight, Hotel, Payment (@nurlaili, @merlin, @anastasia).

QA Engineer / SDET IN PROGRESS

-- SKIPPED ---

Outsource (for monkey works) IN PROGRESS => still on table, discuss separately: @Yussi and @Nazmy

-- SKIPPED ---

BP Nextgen integration effort –> IN PROGRESS

Ideally, the integration will be done by Product
Next Action Point:
PM & Eng Lead to fullfill @agusputri document, https://docs.google.com/spreadsheets/d/1bmZA3adXueCdHDiHYo5RPHqIf94J2mILbjObStanD6A/edit#gid=886735410

Owned by Data Team Report --> IN PROGRESS

Next Action Point:
=> Khresna: will simplify some reports to reduce number of reports under data team pipeline, deposit waiting for Accom
=> Many reports from FBI are still there
=> Merlin will have a meeting with Elsa, together with Khresna, Chriswanto & Aji to discuss reports specific to Accom -->
=> Ale: all reports from financial product are already registered on the spreadsheet.

Share Current Project

@Yussi will setup PMO division to oversees project across stream (in order to identify the dependency of projects in between stream) => grooming under Marc
Next Action point :
In the next meeting will need to share 15 min presentation high level overview of projects that might impact other stream

ERP hotel (with checkin-checkout date)
--> already optimized by @hadi and @radit team from 8 hours to 15min. ERP schedule can be adjusted, so another report can be finished faster.


Tripops decommission:
--> deployment target after release freeze (18 Juni).
--> this week will be testing by @kenny.

Lebaran MEC

Before lebaran: Data from May 1 - May 25 should be available
After lebaran (June 10-12): May 25 - May 31 should be available
for monthly data: it's okay to provide it on June 13
--> on track.