Santa Project Update - 4 February
Please find below the remaining launch blocker tasks from each department and progress updates.
PRODUCT ENGINEERING
Nearest milestone : Production Release for all Services and Tools (blocked by Infra) ETA 22 Feb
- We're currently under development to improve the overall gift voucher security as follow
- Improving Voucher Code generator logic
- Masking and Hiding Voucher Code in all TAP and Gift Voucher tools
- ETA for the security development 22 Feb
- On the other hand, we're also fixing the coupon deduction logic to Flight sales. Which in existing logic will impact Flight report to be negative because the total amount of coupon will also deduct cross sell, insurance and other non FLIGHT_SALES order entry. Still waiting for the estimation from our engineer.
Santa and Product Corp Tech
Nearest milestone : Finance Report Final Testing
- Report Development for Hotel, Refund and Package is currently in testing progress. We are still waiting for each team ETA for testing completion. PIC Yosi, Devy
FLIGHT AND HOTEL REFUND ADJUSTMENT
Nearest milestone : Refund calculation testing
- Flight refund calculation adjustment to exclude gift voucher from refund already completed.
- Meanwhile, for Hotel refund calculation still need additional integration to TDM service for hotel refund. ETA is still waiting for Hotel estimation. PIC David, Dahru
Please find all outstanding items in this list
Please find below the remaining launch blocker tasks from each department and progress updates.
PRODUCT ENGINEERING
Nearest milestone : Production Release for all Services and Tools (blocked by Infra) ETA 22 Feb
- We're currently under development to improve the overall gift voucher security as follow
- Improving Voucher Code generator logic
- Masking and Hiding Voucher Code in all TAP and Gift Voucher tools
- ETA for the security development 22 Feb
- On the other hand, we're also fixing the coupon deduction logic to Flight sales. Which in existing logic will impact Flight report to be negative because the total amount of coupon will also deduct cross sell, insurance and other non FLIGHT_SALES order entry. Still waiting for the estimation from our engineer.
Santa and Product Corp Tech
Nearest milestone : Finance Report Final Testing
- Report Development for Hotel, Refund and Package is currently in testing progress. We are still waiting for each team ETA for testing completion. PIC Yosi, Devy
FLIGHT AND HOTEL REFUND ADJUSTMENT
Nearest milestone : Refund calculation testing
- Flight refund calculation adjustment to exclude gift voucher from refund already completed.
- Meanwhile, for Hotel refund calculation still need additional integration to TDM service for hotel refund. ETA is still waiting for Hotel estimation. PIC David, Dahru
Please find all outstanding items in this list